This month, the follow-up project of the fiber-optic transformation of safe city surveillance in a city was launched. EB-LINK completed the batch shipment of the first batch of additional wiring and aggregation equipment, and the servicePhase III of "Safe City" video surveillance optical fiber transmission of a city's Public Security BureauExtension sections and new points along the project line.

What's in the additional batch?

  • Added end protection under the pole and in the roadside box, pressSingle-mode dual-core armored jumper, anti-mouse jumper, special jumper for Internet cafes, pigtailDistributed in groups with pigtails of the same specifications;
  • The aggregation end equipment is installed uniformly on14-slot box transceiver rack, the slots are pre-allocated and labeled according to the customer link ledger;
  • Each box is packed according to the point group, and the box contains the point list of the group. The construction team will check according to the order, and any missing parts will be reported and reissued on the same day;
  • In addition, spare jumpers are distributed with the box at a rate of about 5% for each group, and they can be replaced if damaged on site.

The delivery pace follows the cutover schedule

Different from the one-time delivery of the first phase, this time the cutover plan is reversed: the first area will arrive three weeks in advance, and the subsequent areas will be rolled out one week in advance to avoid long-term stacking and damage of equipment on the construction site. After the first batch of goods arrived, the customer completed the acceptance and pre-shelving according to the inspection records accompanying the goods. There was no re-testing of the entire batch, and the online rhythm did not stop due to waiting for materials. After the goods arrive, they are stacked in the warehouse according to the box code, and the picking record corresponds to the link ledger number one-to-one to avoid mistaking and loading.

Follow-up supply and consultation

The second batch of equipment is planned to be sent out in early March before the start of the construction season. The stock will mainly be Gigabit single-fiber and dual-fiber transceivers and supporting jumpers, and a two-week replenishment window will be reserved. The labels will be changed to coated weather-resistant materials this time. Integrators who need to check the replenishment order model or request a packing list template can contact EB-LINK 0755-83179002.