This month, EB-LINK has completed a batch of supporting shipments for factory perimeter monitoring and transformation. In addition to gigabit transceivers with power supply capabilities, it also includes box-type transceiver racks and armored lead-down jumpers. All of them are boxed and labeled according to the point list, and the integrator can construct the boxes according to the site.
The difficulty of the project is power collection on the pole side and peak night vision
The perimeter of the factory area is dispersed and there are many lighting linkages. The power when the infrared is fully turned on at night is much higher than during the day. The original solution of decentralized adapters was exposed to concentrated faults after the rainy season. After the transformation, the optical fiber was pulled to the perimeter box, and the pole side was uniformly sent downwards by a transceiver with power supply capability. Only the upstream port was retained on the computer room side. The inspection surface was significantly narrowed, and the number of spare parts was reduced from a dozen models to three. The personnel on duty no longer need to remember which adapter is used in each box. The position of two direction points needs to be taken when going down. This time, useGigabit single mode single fiber 1 optical 1 electrical + 1 optical 2 electrical fiber optic transceiver, if the convergence on the machine room side is put in14-slot box transceiver rackUnified management.
How to coordinate the construction of cartoning and labeling
- The boxes are divided into boxes according to perimeter sections. The point number, cable length and port serial number are marked on the box surface. One box corresponds to a section of fence, and it can be written off after being loaded.
- The rack and downstream multi-port accessories are packaged separately to avoid on-site rummaging.
- Vulnerable jumpers are installed individually in anti-pressure boxes to reduce insertion loss fluctuations caused by construction trampling.
- A point comparison table is included with the machine to facilitate the construction party to backfill the actual length and measured power.
What to follow up after delivery
Each unit comes with actual measurement records one by one, marking the power supply output and port status, which can be compared by number during acceptance. Within a week of arrival, we will return to investigate the situation of power outages and port shutdowns at night, and compare the actual measurement records with on-site readings one by one to determine whether it is a tight budget or a wiring problem. If subsequent similar projects want to adjust the number of lower hanging ports or change to dual-fiber form, they can be proposed in the planning stage. The full range of products can be found atOptical fiber transceiver and switch series.