Project cutover waits for no one, and the arrival time of equipment directly determines the window arrangement. This article clearly explains the delivery time structure of the three dimensions of spot goods, coding and matching, helping integrators to schedule urgent projects more stably.

Spot is not a word, it is three accounts

  • Models in stock: common range modules from 100M to 100G,SFP+ 10G single-mode dual-fiber 10km optical moduleThese high-frequency models are kept in stock, and regular orders can be shipped first;
  • Code types are in stock: custom code writing is based on the basic model, and batch code writing and readback verification require one to three days more than the bare module cycle;
  • Complete set:LC-LC single mode dual core jumper, pigtails and racks are stocked according to common lengths and core numbers to avoid waiting for a whole box of equipment for one jumper.

General path from order to shipment

Small batches of regular models are generally checked, labeled and packaged on the same day; for code-writing batches, the port correspondence table and samples are first confirmed, and the batch is sent after the signature is returned; large-volume items are shipped in batches according to the arrival plan, and are aligned with the on-site cutover schedule. The significance of preparing ready stock is to turn the uncertainty of waiting for production into the inventory cost determined by the factory, so that the delivery date can be negotiated and promised.

Four actions for planning delivery on the purchasing side

  • Determine the distance gear and wavelength before making an inquiry to avoid shifting gears and rework after arrival;
  • A buffer of about one week is reserved for coding and customizing specifications;
  • Place orders in batches according to the cutover window, and those who are cut over first will receive the goods first;
  • For small items such as jumpers and adapters, add 10% to 20% of the required amount.

The core of delivery management is to figure out what is in stock and what needs to be produced. There are 282 models for sale on the EB-LINK site. For emergency renovation projects, you can first call 0755-83179002 to confirm the range of stock and then set the construction window.