One-time arrival may seem like a hassle-free process, but in fact it will put the pressure of sorting, acceptance and termination in the same week. The issue of batch delivery is to solve the problem of rhythm. If the order is wrong, it will delay the construction period.
Take construction sites as the first batch
The basis for judgment is not the distance, but the conditions of the computer room: whether the power supply, distribution frame and optical cable are in place. The first batch will only be issued to these offices so that acceptance and termination can be carried out simultaneously. Commonly used in access sections with relatively fixed speeds and gearsSFP Gigabit single mode dual fiber 10KM optical module, can be issued in batches first, and the long-distance models of cross-region convergence segments can be placed in subsequent batches.
Set aside time for report and ledger handover for each batch
- Check the batch number and individual test reports on the day of arrival, and complete random inspections before signing for receipt.
- The port correspondence table shall be handed over to the construction team one day before the cutover to allow time for familiarization.
- The installed capacity of this batch and the remaining pool positions are written back to the ledger simultaneously as the basis for the next batch of quantities.
- For short-distance interconnection in the computer roomSFP Gigabit Multimode Dual Fiber Optical Module, it arrives together with the short jumper.
It is recommended to leave a buffer of at least one week between batches to deal with the rectification of ports with high termination losses. After the rectification is completed, the next batch of cutovers will be scheduled.
Leave a reissue window instead of reissue at any time
Set up a fixed reissue batch before the end of the project, and combine scattered missing parts with model adjustments. Temporary reissues can easily lead to repeated expenses on transportation and documents, and can also cause gaps in the receipt ledger. YesSFP+ 10G single-mode dual-fiber 40km optical moduleSuch models with long delivery times will be reserved according to the upper limit in the first batch.
EB-LINK can arrange the shipment batches according to the project cutover plan. For batch communication, you can call 0755-83179002. It is recommended to review the first batch of quantities together.